New Project Update

May 12, 2026

Project Update

Mohawk Tannery Remediation Update – Q4 2025 & Q1 2026

Work has accelerated at the Mohawk Tannery site from December 2025 through April 2026, with major site preparation, sludge excavation, and early containment system construction now underway.

1. Summary of Work Completed

  • The Mohawk Tannery project site has undergone a visible transformation from wooded/overgrown conditions to an active construction site.
  • The initial site preparation was completed; including clearing vegetation/debris and removing invasive species in work zones, creating access roads, and developing the necessary work zones, including relocating and consolidating asbestos debris.

Aerial view of active excavation showing the development of access roads and the necessary work areas

  • Excavation and relocation of Sludge Area 3 to the containment area.
  • The safety systems for both internal worker safety and adjacent neighborhood safety (ie air monitoring stations and erosion control measures) were installed and remain fully operational.
  • All construction vehicles now enter and exit via Veterans Memorial Parkway rather than through neighborhood streets.
  • The early preparation for the containment system has begun.
Concrete being pumped into the guide wall for the eventual containment system to be built above the 500-year flood zone

2. Upcoming Work over the Next Quarter

  • Continued relocation and consolidation of asbestos debris.
  • Demolition and removal of former tannery building foundation (mid–late May). This work will involve heavy equipment and will be louder than typical site activity for a period of time.
  • Crews will continue ongoing site maintenance, debris removal and grading refinement of various work areas.
Excavation and movement of soils will progress into spring 2026 reshaping the land for eventual development

  • Activities will continue for the construction of the underground containment system as well as material handling and preparation for the next phase of remediation.
  • Start of installation of the underground secant pile wall.

Anticipated Impacts

  • Increased construction visibility & traffic across the site.
  • Temporary elevated noise levels during foundation demolition.

Ongoing Mitigation Measures

  • Continuous perimeter air monitoring to ensure safe air quality levels.
  • Erosion and stormwater controls maintained across the site.
  • Construction traffic routed exclusively via Veterans Memorial Parkway.
  • The work is conducted exclusively within permitted hours of each zone.

Project Site Manager Michael Paonessa inspects Air Monitoring Station near the Fairmount St Gate (which is no longer used by Construction as all vehicles enter via the Parkway)

Pedestrian Bridge

  • The City of Nashua has long contemplated the construction of a pedestrian bridge connecting the neighborhoods of Little Florida and Fairmount Heights to Mine Falls Park.
  • Blaylock and the City of Nashua have agreed to partner to ensure recreational plans set in the 1970’s finally come to fruition.
  • Blaylock has begun preliminary design analysis with various engineers to begin the permitting and eventual construction of the bridge.

Rendering of the vision to connect the surrounding neighborhoods to the 325-acre crown jewel of the Nashua Park System

Sign up to
receive updates

Sign uP
Two workers checking phone
Contact us

Stay in the loop